Industrial Piping, Inc., Mayo Power Plant – Zero Liquid Discharge System

Exterior of Mayo Power Plant

MBP provided dispute resolution services including reviewing and providing opinions on the claimed schedule delays and costs, and providing support to counsel in preparation for and at mediation. The power plant project involved the fabrication of a zero liquid discharge process system for Progress Energy.

Jeffrey Energy Center

Exterior of Jefferson Energy Center

MBP provided dispute resolution services for the Jeffery Energy Center. The project involved selective catalytic reduction process, additions, and alterations to the existing Jeffrey Energy Center coal-fired electrical power plant.

Kaiser Aluminum, Gramercy Refinery Digester Rebuild

Aerial view of Gramercy Alumina Refinery

MBP became involved in the project on behalf of the owner during the reconstruction of the digester area of the Gramercy Alumina Refinery after it was destroyed in a catastrophic explosion involving high-pressure piping and pressure vessels. MBP provided on-site inspection, CPM scheduling, cost to complete estimates, analysis of the actual costs of performance, expert… Read More

Liberty Place II, Hotel, Retail, and Office Tower

Exterior of Liberty Place

MBP provided dispute resolution services including detailed research of project documentation, as-built vs. as-planned, CPM schedule delay, acceleration analysis, and provided expert testimony in arbitration proceedings and support to counsel in the preparation of interrogatories and during depositions. This mixed-use building complex consists of a 60-story office building, 16-story luxury hotel, two-story retail facility, and… Read More

Marsh Run Electric Generation Plant

Exterior of Marsh Run Electric Generation Plant

MBP provided expert witness analysis and testimony services for the new 680 megawatt electric generation power plant including three combustion turbines capable of running by both natural gas or diesel fuel and all utility and plant infrastructure.

NCDOT, Yadkin River Bridge

Aerial view of construction of Yadkin River Bridge

MBP provided dispute resolution services for this design-build project which included the replacement of the bridge that carries I-85 over the Yadkin River, the parallel bridges that cross over the North Carolina Railroad tracks located north of the river, the parallel bridges over the Duke Power Industrial Rail Spur located south of river, and the bridge… Read More

New York Law School

Exterior of New York Law School

MBP provided litigation support leading to two negotiated settlements for the New York Law School’s new community facility. This glass enclosed, 235,000-square-foot, nine-story structure doubles the size of the law school’s campus, and includes classrooms, an auditorium, conference and study rooms, libraries, lounges, a dining facility, administrative, and event and operations space for the New York… Read More

North Carolina Department of Justice, Virginia Dare Memorial Bridge

Aerial view of Virginia Dare Memorial Bridge

On behalf of the North Carolina Department of Transportation, MBP reviewed the contractor’s claim for additional compensation and time extension. The Virginia Dare Bridge is a new 8.4 kilometer structure that connects Roanoke Island and North Carolina’s Barrier Islands in Dare County, North Carolina. The project spans wetland areas near the shore on the east and west sides… Read More

Pike and Rose Mixed-use Development

Pike and Rose

MBP provided dispute resolution services for Block 10 and Block 12 of Mid-Pike Plaza. Block 10 is a 19-story, high-rise residential building with an exterior consisting of brick, cast stone, and aluminum punch windows. Block 12 is a four-story mixed-use residential/commercial building.

Raleigh-Durham International Airport Parking Garage

Raleigh-Durham International Airport Parking Garage

MBP performed dispute resolution services including the investigation and technical analysis of disputed issues and delays related to the new 2,700-space, multi-level parking garage and connecting tunnel at the Raleigh-Durham International Airport. Phased construction included two concrete deck structures consisting of slab-on-grade, four supported levels of post-tensioned concrete, two steel vehicular helices, and a covered open-air lightwell… Read More